ODI 12c - Activate or Deactivate your schedule on load plan

Here we will show the steps to activate or deactivate your schedule created on load plans.

Steps:

Step1: Go to Operator tab -- Scheduling -- All Schedules -- select your schedule and expand and rightclick on Golbal/logical agent -- open


Step2: select status Active or inactive and save.


Step3: Go to Load plan and Scenarios -- double click on your load plan

Step4: Enable or disable the steps. Generally need to disable or enable 1st parent steps.

Why we need to disable or enable steps in load plan:

Sometimes we see that though you have inactivated the schedule, still its running so to avoid this scenario, we can also disable the steps in load plan as well.