ODI 12c - CKM with Flow control and Static control and Recycle errors

Here, we will show the setups required for Flow control , Static control and Recycle errors.

Brief steps:

1. Create a Primary key constraint on target data store.

2. Create a map and Select flow or static or recycle errors option

Flow diagram for LKM, IKM,CKM:



Implementation steps:

Step1: open the target data store constraints and control tab to checj if there is any duplicate rows.




Step2: Create  a new map and prividd LKM, IKM and Flow control as False and Statc control as true and run. You will see the the duplicate or null errors in E$_EMP table.









Step3: Now make Flow control also True


Step4: Now make Recycle errors as True






Monday, October 25, 2021

ODI 12C - CDC implementation using JKM

Here, we will see how to capture changed data(New inserted data and update data) using JKM and send the data to Target.

Implementation steps:

Step1: import JKM 


Step2: model -- Journalizing -- select Journalizing mode . Here choosing Simple and select KM.


Step3: Open Datastore and constraints -- create primary key as empno.


Step4: EMP datastore -- CDC -- Subscriber -- subscribe. Add one subscriber.


Step5: Add to CDC


Step6: Start Journal ans select subscriber.



Step7: you can check that Subscribers will be created and J$ and JV$ tables.






Step8:
add emp table in the journalized table.

Step9:
do the mapping Nd select subscriber in the logical Journalizing section

Step10:
Add LKM and IKM and flow control as false.



Step11:
select source unit and check the option Journalized Data only.


Friday, October 22, 2021

ODI 12c - Manually run a load plan if schedule not worked automatically

If schedule does not work automatically then we can run the load plan manually.

Steps:

Operator tab →Load plans and scenarios →select your load plan→ right click on and run and select your agent and ok.


ODI 12c - Procedure and use options

Procedure in ODI:

  • A procedure in Oracle Data Integrator (ODI) consists of a series of commands executed in sequence. Commands contain code that can be executed by database engines, the operating system where the Agent is running, or directly by ODI. 
  • You can also define options in the procedure to control its behavior at run time. A very useful property of procedures is that they are reusable and can be inserted into packages. Thus, just as procedures comprise commands, a package can contain several procedures as steps.
  • You use procedures in a package or a scenario, or you can run them directly from the Designer Navigator.

Implementation Steps:

Step1: Designer -- Projects -- your project -- procedure -- new procedure


Step2: Define Procedure name, and source and target technology if needed.


Step3: Tasks -- Add new task


Step4: Created couple of tasks. For 1st task provide name


Step5: Target command -- select technolgy, context, logical schema, and command.


Step6: Need to provide source command if you want to select some fields.

Step7: Mention the same for remaining 2 commands




Step8: For this 3rd command, used source command to select the data from source emp table.


Step9: Assign the selected source fields in the target insert values using :fieldname



Step10: Save and run it.


Note: Select the Ignore Errors check box so that the procedure runs even if this command fails.

Step11: To use options, go to Options and add option


Step12: Added 3 options


Step13: Go to Tasks and option section and select the options to be used for a particular task.

Featured Post

11g to 12c OSB projects migration points

1. Export 11g OSB code and import in 12c Jdeveloper. Steps to import OSB project in Jdeveloper:   File⇾Import⇾Service Bus Resources⇾ Se...