Thursday, October 21, 2021

ODI 12c - Activate or Deactivate your schedule on load plan

Here we will show the steps to activate or deactivate your schedule created on load plans.

Steps:

Step1: Go to Operator tab -- Scheduling -- All Schedules -- select your schedule and expand and rightclick on Golbal/logical agent -- open


Step2: select status Active or inactive and save.


Step3: Go to Load plan and Scenarios -- double click on your load plan

Step4: Enable or disable the steps. Generally need to disable or enable 1st parent steps.

Why we need to disable or enable steps in load plan:

Sometimes we see that though you have inactivated the schedule, still its running so to avoid this scenario, we can also disable the steps in load plan as well.

No comments:

Post a Comment

Featured Post

11g to 12c OSB projects migration points

1. Export 11g OSB code and import in 12c Jdeveloper. Steps to import OSB project in Jdeveloper:   File⇾Import⇾Service Bus Resources⇾ Se...